Case Studies
Building Materials Distributor
This nationwide building materials distributor operates numerous facilities in the USA.
Profile of this specific operation is characterized as:
| Operation Profile |
| Location: |
Western USA |
| Truck count: |
65 |
| Shift description: |
10
hrs/shift;
2 shifts/day;
6.5 days/week |
| Previous
battery charging and changing
operation: |
- 2.2 batteries/truck
- All trucks change batteries
during each shift
|
| Minit-Charger
Solution |
| New battery
fast charging solution: |
Seven 2 station
chargers; Seven 3 station chargers;
Six 5 station charger |
| Operating
savings over current battery
changing and charging: |
- 6 years: 71%
- 9 years: 76%
|
| Payback
period: |
1.3 years |
Food Processor & Distributor |